Shell, Structure, Staves, Equipments, Pipelines - 1800 Ton
Shell, Structure, Staves, Equipments, Pipelines - 1800 Ton
SUCCESSFULL COMMISSIONING
Assembly, Erection and alignment and commissioning of TG building Equipment's - 1900 MT
Assembly, Erection and alignment and commissioning of TG building Equipment's - 1900 MT
Fabrication, Erection and alignment of Technological structure (ESP process duct) - 500 MT
EQUIPMENTS- CONCENTRATE FILTERS - Erection and Alignment - Tonnage - 280 MT
TOWER MILL - Erection and Alignment - Tonnage - 160 MT
Fabrication, Erection and Alignment of Thickener and its Structure. - Diameter- 36 Mtr - Tonnage – 160 MT
TECHNOLOGICAL STRUCTURE Like Dump hoppers, Cloth washer Tank, Mag collection sump, Scalping cyclone sump - Fabrication and Erection - Tonnage - 280 MT.
AIR RECEIVER TANKS - Fabrication, Erection and Alignment - Tonnage - 70 MT
PIPE and CABLE GALLERY - Fabrication and Erection - Tonnage - 250 MT
MAG BUILDING - Fabrication and Erection - Tonnage - 400 MT
ROM Conveyor - Erection and Alignment - Tonnage - 200 MT
Fabrication, Erection and Alignment of Slurry Tank - Diameter - 15 mtr, Height - 17 Mtr
- Erection and alignemnt of Tailing filter press equipment- 350 MT
- Fabrication and Erection of Tailing building structure- 250 MT
Manufacturing, Supply and Erection of RHF- 250 MT - i) Body structure ii) Walkways iii) Equipment's v) Combustion air duct and structure
Manufacturing, Supply & Erection of RHF i) Chimney ( 4.5 mtr dia at bottom & 80 mtr height)-Natural draught -150 MT i) Waist Gas Duct- 80 MT
Fixing of anchors for Refractory in i) Inside RHF body structure ii) Skid pipes iii) Flow Gas duct ii) Chimney, chute, etc and Pipeline work, Total Tonnage - 800 MT
Installation, Alignment and Commissioning of Wire Rod Line Equipment's Tonnage - 650 MT
Installation, Alignment and Commissioning of all CHA Equipment's Tonnage - 600 MT
Dismantling, Shifting, Assembly and Re-Installation of EOT Crane Including Electrical wiring - Capacity - 25 Ton
Production- 5000 MT/Month Capacity : 7000 MT/Month
Supply and Erection of Visitor Gallery, PRL Walkways and Walking Beam Platform – Tonnage : 150 MT
Fabrication and Erection of RMS Shed - Tonnage: 4000 MT - Avg Output - 400 MT/Month - Total Tonnage - 4000 MT
SS Coil Carrier Spiders: To carry the hot coil in furnace - 42 Nos
SS Coil Carrier Spiders: To carry the hot coil in furnace - 42 Nos
Production- 1500 MT/Month - Capacity: 1500MT/Month
Fabrication and Erection of Chimney a) Height- 50 mtr b) Dia- 4.5 mtr c) Weight- 250 MT d) Qty - 2 Nos
Erection, Alignment and Commissioning of Stamping Machine- 150 MT (With laying cleaning pickling and Flushing of Hydraulic Pipe line)
Erection, Alignment & Commissioning of Conveyors and Equipments- i) Belt Conveyors ii) Grizzley iii) Hoppers iv) Crusher house v) Screeners vi) All Type of Chutes vii) Rod gates viii) Bag Filters.
Fabrication of Ladle with Trunnion
1.Consultancy, Fabrication & Erection of steel structure for washing and crushing plant at RIPL Site. 2.Engineering & Consultation service including Basic Engineering, Detail engineering & Layout Finalization, Process Flow Development, Mass water & FE balancing, Detailed Engineering (BOQ), Drawing & Documents, Pipe Line 2 D Drawing, 2D P & ID Drawing, Control Philosophy, Commissioning Assistance. 3) Iron ore slurry line design, engieeirng, supply & commissioning- about 2 Km & flow 150 Cu.m/Hr 4).Structural steel Fabrication, Erection – 400 MT. Note: This plant is Re-constructing at another location due to Forest issue.
Thickner Shifting - BE, DE & Construction done by Palmet
DESIGN, MANUFACTURING, ERECTION AND COMMISSIONING OF WASHING PLANT- 180 MT
Installation and Commissioning of Beneficiation Plant of capacity 1 Million Ton Plant of BHQ Feed grade of 44 & upgrading to > Fe 63. Tonnage a) Equipment’s- 1500 MT b) Structure – 2500 MT, c) Civil- 10000 Cu.m
Fabrication and Erection of De-Dusting unit and Structure. (140 MT)